Weir River Water System

Posted on: October 3, 2021

[ARCHIVED] Atlantic / Gunrock Ave, Hull - Water Main Replacement Project

On Monday, October 4, 2021, the Weir River Water System (WRWS) will be begin mobilization of the Atlantic-Gunrock Ave water main replacement project. The plan is in three-phases in the order listed below for approximately 8-10 weeks. 

Atlantic Ave West – Nantasket Ave to #205 Atlantic Ave – week 1-4

Atlantic Ave East – Cohasset Line to #128 Atlantic Ave – week 4-8

Gunrock Ave – entire length of street – week 8-10

CONTRACTOR: C NAUGHTON CORP, BRIDGEWATER MA

508-807-1241

Work Schedule: 7:00 AM – 5:00 PM

PN - Atlantic-Gunrock Ave Project