Over the past two weeks C. Naughton has been installing 12-inch ductile iron water main on the eastern end of Atlantic Avenue from Gun Rock Ave to the Cohasset Line. We also had additional crews on site completing side street water main connections and domestic water service transfers on the western end of Atlantic Avenue. These connections are being schedule by C Naughton with each individual resident.
During the week of December 20, 2021, we will be continuing to install 12-inch ductile iron water main on the eastern end of Atlantic Avenue towards the Cohasset line and some cleanup work on Gun Rock Ave. There are no schedule side street connections, service transfers, or interruptions in service this week. All trenches will be completely paved and the site cleaned up at the end of the week in preparation for the holidays.
PLEASE BE ADVISED THAT C NAUGHTON WILL SHUT DOWN DURING THE WEEK OF DECEDMBER 27TH AND RESUME WORKS AFTER THE NEW YEAR.
Thank you all for your continued cooperation and support during this much needed water main project. Should you have any questions or concerns, please do not hesitate to contact us:
Russell E. Tierney, Managing Director/Superintendent, WRWS
Phone: 781-804-2304 Email: tierneyr@hingham-ma.gov