Last week KRR installed new 12" water main just south of the intersection of Planters Field Lane up to House #70. We ran into some ledge and a conflict with the existing water main so will move the project down the street and start installing water main on Downer Ave from Crow Point Ln towards Lincoln St. Over the next several days we will work to address the conflict and come up with a resolver by the end of the week.
If you have any question please do not hesitate to contact Russell E. Tierney, Managing Director / Superintendent, at 781-804-2304 or tierneyr@hingham-ma.gov.
Locus of Work - Week of 8-14-23